State Auditor Report Questions High-Speed Rail Funding, Oversight, Ridership Projections

Save ArticleSave Article
Failed to save article

Please try again

Being a high-speed rail official getting that first glimpse of yet another government report on the project must be like Kyle Williams opening up an email with the subject line: "Your performance in the NFC Championship."

To the growing library of official criticisms, add another disapproval today of the way the California High-Speed Rail is handling things.

Tweeted by KQED's John Myers:

https://twitter.com/#!/KQED_CapNotes/status/161859354021203969

Sponsored

For previous slams at HSR by various watchdogs, see here, here, and here.

Included in the project's litany of woes: Today's report comes a couple of weeks after the resignation by the CEO of the California High-Speed Rail Authority, Roelof van Ark; a December poll showed about two-thirds of voters would now vote against issuing HSR bonds; Sen. Dianne Feinstein has called on CalTrans to take over the beleaguered project; Republicans, both state and federal, are looking to gut the entire thing; and even former staunch supporters have expressed doubts.

On the positive side, Gov. Jerry Brown gave a strong defense of HSR in his recent State of the State speech.

Key findings and recommendations from today's released report by the auditor below. You can read the full report (pdf) here.

KEY FINDINGS

During our review of the Authority’s progress in addressing issues we raised in our April 2010 report, we noted the following:

• The program’s funding situation has become increasingly risky—in its 2012 draft business plan, the Authority estimates that phase one of the program will cost between $98.1 billion and $117.6 billion, yet has only secured about $12.5 billion to date.

-The plan has not identified viable alternatives in the event that its planned funding sources do not materialize—it relies heavily on securing tens of billions of dollars of federal funding, yet fails to present specific steps for acquiring these or other funds.

-The plan lacks key details regarding costs and revenues which compromises the Authority’s transparency.

*The full cost of the program is not clearly presented and the operating and maintenance costs for phase one, which we estimate to be almost $97 billion, are not included in the plan.

*The Authority projects securing private sector investments over four years beginning in 2023 yet did not specify in the draft business plan that this is based on the concession that private sector investors will receive all of the program’s net operating profits from 2024 to 2060 in return for their investment.

-The success of the program hinges largely on the accuracy of its ridership projections—fundamental to the revenue projections and to private investors’ interest in the program. However, the Authority has not fully addressed questions about the accuracy of the model’s long-term projections.

• The Authority may have compromised providing effective oversight by placing the largest portion of the program’s planning, construction and oversight in the hands of contractors—in particular, the entity that manages the program (Program Manager).

• By relinquishing significant control to the Program Manager, the Authority may not be aware of or have addressed areas of significant concern that could impact the program.

-Similar to our prior audit, we found over 50 errors and inconsistencies of various types in three Program Manager’s monthly progress reports we reviewed and noted several significant discrepancies between the regional contractors’ reports and those of the Program Manager.

• The Authority inappropriately split its information technology (IT) services valued at $3.1 million into multiple contracts—rather than competitively bid the contract—when it renewed its IT services. In addition to the initial contract, the Authority used 13 individual contracts over a 15-month period that ranged from $105,655 to $249,999.99 for similar services with one vendor.

KEY RECOMMENDATIONS We made several recommendations to the Authority to ensure the public and the Legislature are aware of the full cost of the program including that it clearly reports total costs and discloses all assumptions in its funding and cost estimates. The Authority should continue to fill positions to decrease its reliance on contractors and ensure its Program Manager’s progress reports are consistent, accurate, and useful. To manage its contracts effectively, the Authority should develop procedures to detect and prevent contract splitting.

For more on on the current shaky status of the project, watch the following "This Week in Northern California" video from last Friday:

Update 12:51 p.m. Take note of this Tweet today from KCBS' Doug Sovern:

https://twitter.com/#!/SovernNation/status/161912593689214977

lower waypoint
next waypoint
California Preschools Wrestle to Comply With State’s Tightened Suspension RulesSan Francisco’s New Parking Rules Set to Displace RV Community Near SF StateA New Bay Area Clásico? SF's El Farolito and Oakland Roots Set to Battle in HaywardWhy Nearly 50 California Hospitals Were Forced to End Maternity Ward ServicesStunning Archival Photos of the 1906 Earthquake and FireWhat the 99 Cents Only Stores Closure Means to CaliforniansDemocrats Again Vote Down California Ban on Unhoused EncampmentsFederal Bureau of Prisons Challenges Judge’s Order Delaying Inmate Transfers from FCI DublinCalifornia Legislators Take Aim at Construction Fees to Boost HousingFirst Trump Criminal Trial Underway in New York