upper waypoint

Muni, AC Transit Chiefs Call for Further Review of Transit Center Issues

Save ArticleSave Article
Failed to save article

Please try again

A section of one of two cracked steel beams that forced the closure of the Transbay Transit Center in September. (Transbay Joint Powers Authority)

Two transit officials whose agencies operate out of the new Transbay Transit Center said Thursday they'd like to see a thorough independent review of the facility, which was closed six weeks ago after the discovery of cracked steel beams in the structure.

Ed Reiskin, head of the San Francisco Municipal Transportation Agency, and AC Transit General Manager Michael Hursh raised the issue as the Transbay Joint Powers Authority board discussed progress in tracking down the cause of the cracked beams. Both Hursh and Reiskin serve on the board.

Reiskin pointed out that the damaged structural steel, located beneath the $2.2 billion center's bus deck at a point where it crosses over Fremont Street, was discovered "serendipitously" by a crew working on the building in late September.

"Given that we found this just by chance begs the question, what other things might there be in the building that we should be looking at to make sure there's not something else that may have been missed," Reiskin said.

TJPA Executive Director Mark Zabaneh responded, "We can go back and develop a strategy," adding that agency staff would review work "to make sure everything was done to plan."

Sponsored

"The emergence of this issue kind of puts at stake the credibility of the whole project," Reiskin said. "I think we need some level of review, maybe some level of independent review, of the whole facility. ... I think having that review undertaken will be important to restore the credibility of the facility."

Hursh said AC Transit, which had operated service to the new center for only six weeks before the abrupt Sept. 25 shutdown, needs to be able to reassure its patrons and staff about the facility's safety.

"We're currently carrying over 14,000 people a day" to a temporary terminal at Folsom and Beale streets, he said. "A bus operator is going to have to explain to those 14,000 people why it's safe to come back. That should be the goal of this study -- for us to be able to in plain language explain to the customer and our employees why it's safe and why we're comfortable going back into the facility."

The investigation into the two cracked steel I-beams includes a peer-review panel of engineering experts appointed by the Metropolitan Transportation Commission. Besides helping look for the cause of the fractured steel, the panel will also consult on what steps are necessary to replace or repair the damaged beams and is charged with identifying other structural issues that may need attention.

Board members suggested additional study could come from the American Public Transportation Association, which runs a peer-review program for transit agencies

A materials lab in New York state is currently conducting a battery of tests on samples sawed out of the two fractured metal beams. Agency staff told the board those tests could be completed next week. After they're analyzed and the likely cause of failure identified, project experts and the MTC peer-review team will consult on how to address the problem and design a fix.

That process could continue for weeks, Zabaneh and his staff said. Only when the TJPA understands the scope of the needed repairs will the agency be able to say when the transit center can reopen.

"We will not open the facility without insuring that the structural integrity of the building is sound," Zabaneh said.

The steel issue and other problems with the transit center project recently prompted the San Francisco County Transportation Authority board to halt funding that the joint powers authority needs for its next high-profile project: the long-planned Caltrain extension from its current terminal at Fourth and Townsend streets through downtown to the transit center.

"The organization that developed the Transbay Terminal is out of its depth, out of its league and needs a new governance structure," Supervisor Aaron Peskin said before the vote on the funding. "I think it's time to rethink this to make sure we have an organization that can actually deliver a remarkably complex project."

Under current projections, the downtown extension would cost about $6 billion and be finished in 2026 or 2027.

lower waypoint
next waypoint
At Least 16 People Died in California After Medics Injected Sedatives During Police EncountersPro-Palestinian Protests Sweep Bay Area College Campuses Amid Surging National MovementCalifornia Regulators Just Approved New Rule to Cap Health Care Costs. Here's How It Works9 California Counties Far From Universities Struggle to Recruit Teachers, Says ReportWomen at Troubled East Bay Prison Forced to Relocate Across the CountryLess Than 1% of Santa Clara County Contracts Go to Black and Latino Businesses, Study ShowsUS Department of Labor Hails Expanded Protections for H-2A Farmworkers in Santa RosaAs Border Debate Shifts Right, Sen. Alex Padilla Emerges as Persistent Counterforce for ImmigrantsCalifornia Law Letting Property Owners Split Lots to Build New Homes Is 'Unconstitutional,' Judge RulesInheriting a Home in California? Here's What You Need to Know